Projects

Rational fire protection for an unconventional building

Texte Philippe Selke | Photos Le Sprinkler rationnel

Dans une telle icone architecturale, les conduites et les sprinklers eux-mêmes devaient donc se faire le plus discret possible.
Dans une telle icone architecturale, les conduites et les sprinklers eux-mêmes devaient donc se faire le plus discret possible.

A visit to the 11 levels of this one-of-a-kind building confirms it: everything about the former Royale Belge is unconventional, from the ceiling layouts and the way each occupant has fitted out their office space to the heritage character of some communal areas and the combination of so many different functions within a single structure. From the basement to the upper floors, Le Sprinkler rationnel drew on its experience and remarkable adaptability to ensure effective sprinkler fire protection in every last corner.

The pipes run through areas with “waffle” ceilings, requiring precise setting-out to align them as elegantly as possible with the structural elements.

Founded in 1982 and certified to ISO 9001, VCA and BOSEC, Le Sprinkler rationnel has specialised in sprinkler fire protection systems for more than 40 years. Its services range from feasibility studies, engineering with 2D and 3D plans and hydraulic calculations, and pipework prefabrication in its own 2000 m² workshops in Brussels or in collaboration with long-standing partners, to network installation and system maintenance. 

“We proposed different installation options, for example using existing holes in the beams, as well as different finishes and colours for the sprinklers and pipes where bright red was not aesthetically desirable.”

“There wherever sprinklers are installed”

The company installs all types of sprinkler system (wet, dry, pre-action, deluge, …) and water supplies in any building where they are required, including offices, car parks, hotels, industrial buildings, warehouses, pharmaceutical, petrochemical and nuclear facilities…

Benoit Poupart joined the company founded by his father in 2005 and works there as a Project Engineer alongside around 15 colleagues. He oversaw the “Royale Belge” project from start to finish while completing another mega-project: the BNP Paribas Fortis headquarters at Montagne du Parc in Brussels. His extensive experience of large-scale projects proved invaluable in eliminating any margin for error on a project as complex as the Mix and the different functions it houses. 

The entire sprinkler protection system is supplied from a very small basement room.

Unconventional in every respect

Benoit Poupart: “It’s truly unique to have offices, a hotel, coworking space, car parks, restaurants, archives and various plant rooms in a single building, some of which is also listed. What’s more, it is a high-rise building, with the specific fire protection requirements that entails. The existing building was protected by sprinklers in only a few isolated areas, and we were the ones who had worked on it back then.”

This architectural icon is an interesting mix of concrete and steel structures, particularly in its renovated atrium, which includes listed elements. The pipes and sprinklers themselves therefore had to be as unobtrusive as possible. “We proposed different installation options, for example using existing holes in the beams, as well as different finishes and colours for the sprinklers and pipes where bright red was not aesthetically desirable. This requires a little more preparation in the workshop, but we aim to integrate as seamlessly as possible with the existing building.” The building is also unconventional in… how few of its ceilings are flat. Changes in level are found everywhere, and the pipes and services have to follow them, as well as the “waffle” ceiling areas, which required precise setting-out to align the pipes as elegantly as possible with the structural elements.

Le Sprinkler rationnel prefabricated the pipework in its own 2000 m² workshops in Brussels.

Flexibility and adaptability

The company’s experience, along with its practice of fully prefabricating systems in its workshops, enabled it to manage the countless changes that arose during construction. For example, although the office floors were initially planned as open-plan spaces throughout, each occupant ultimately fitted out their space in their own way, adding numerous partitions or “boxes within a box”. This changed the sprinkler layout. There was no copying and pasting from one floor to the next, or even from one wing to another, but rather a series of separate projects within the project. Even the hotel section of the Mix is unconventional, with a mix of different room types on every floor.

Work began in late 2021 and quickly became collateral damage from the war in Ukraine, with shortages and soaring prices as a result. To keep work moving and meet deadlines, Le Sprinkler rationnel stockpiled large quantities of materials. As construction progressed, the original order was supplemented by others covering additional areas of the building, including the vast basement levels, which house, among other things, archive rooms requiring a higher level of protection than originally anticipated.

“We always prefabricate in our workshop, and that is our strength. On this project, it proved particularly useful when we needed to increase output. We standardised the pipework sizes as much as possible so that we could cut entire bundles of pipes, up to 60 at a time, in a single operation. We then delivered the materials to site zone by zone, sometimes bringing them in through very restricted openings or passageways. The large workforce we deployed for the installation allowed us to install the networks in different areas in parallel.”

The project’s development over time also affected the other building services, which had to adapt as well. Since sprinklers must not be obstructed, several areas required repeated studies as the project evolved, including coordination with ventilation ducts, to avoid having to redo the installations on site. More generally, coordinating with the other contractors on site required considerable care, but everyone showed great willingness to cooperate, aware that they were contributing to a project that would attract attention.

Drawing on his experience, Benoit Poupart shared the problem areas with the inspection body ANPI at an early stage to find suitable solutions. In the end, the inspection raised only a few minor points, which were quickly and easily resolved, despite the variety of situations and the scale of the project. As proof of the client’s satisfaction with the work completed, it has already asked Le Sprinkler rationnel to carry out additional studies for other areas of the building.    

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow