News

620 km of cables for the world’s largest tropical greenhouse!

Texte Philippe Selke | Photos Arno Louwagie

620 km of cables for the world’s largest tropical greenhouse!

Electrically equipping the world’s largest tropical greenhouse was no ordinary construction project. For the teams at Collignon, a subsidiary of Eiffage Énergie Systèmes - Belux, the main challenge was adapting to a project in constant evolution, where technical solutions had to be continually adjusted to accommodate the architects’ creative ideas.

Covering 4.5 hectares, the greenhouse is home to a wide variety of spaces: hotel rooms, restaurants, animal areas and visitor routes. Behind this immersive experience lies a complex, demanding infrastructure that required no fewer than 620 kilometres of cable. For Christophe Lahaye, Deputy Managing Director of the buildings and industry divisions at Eiffage Énergie Systèmes - Belux, the project stands out for several reasons: its scale, complexity and the mobilisation of the teams. “It is undoubtedly one of the most remarkable projects carried out by Collignon,” he says.

A complete installation package

Working from the engineering firm’s plans, the teams carried out the detailed design and then installed the complete electrical systems. Work began once the glass roof was in place, and continued beyond the opening ceremony to incorporate the final requested changes. The package covered all electrical systems: low- and extra-low-voltage installations, medium-voltage substations with emergency generators, distribution boards, fibre-optic cabling and data networks. It also included specialist installations such as room automation, access control, decorative lighting and evacuation sound systems. Fire detection presented a particular challenge too. Conventional detectors could not be installed at a height of 25 metres, so an aspirating system was used instead, with almost 4.6 kilometres of tubing continuously analysing the air in a humid environment. At the busiest point, as many as 70 to 75 people, including subcontractors, worked on site at the same time for more than six months.

A project in constant motion

One of the main challenges was not just technical, but organisational. The project did not progress in a linear fashion, but followed the pace of work on the buildings and garden, changes to the themes and coordination with the other trades.

“We had to manage extensive simultaneous working at all times, while remaining flexible enough to accommodate the client’s new requests,” explains Quentin Jacobs, Department Manager in the buildings division at Eiffage Énergie Systèmes - Belux. There were many such adjustments. The addition of two food outlets just one month before handover required last-minute changes. Even in the days leading up to the opening, teams were still working on site, drilling through structures to route new cables. In total, more than a hundred changes were made to the electrical distribution boards after delivery, far exceeding usual standards. Some constraints were also related to the nature of the equipment installed: artisan-made light fittings, unusual materials and decorative features that required bespoke fixing solutions.

A collective success

Despite the constraints, pressure and constant adjustments, the project was carried out in a strong spirit of collaboration. Everyone involved shared a common goal: to deliver a project that was both technically demanding and unusual. In the end, beyond the impressive figures, this project above all demonstrates the teams’ ability to adapt, innovate and work together in a complex environment. For many, it will remain a benchmark.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • ThemeSafe and adaptable electrical installations
  • SubjectNews
Share this article

Follow Installation & Construction

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.